Highway work under way

By   /   Friday, September 19th, 2008  /   Comments Off on Highway work under way

    Print       Email

A project to repave two sections of Highway 246 was scheduled to start Sept. 19 in the following locations, weather permitting:
 

• from Hill Haven Road to Via Juana Road;

• from Edison Street to the Highway 154 interchange.

This work will take place from 8:30 a.m. to 4 p.m. Monday through Thursday and from 8:30 a.m. to 2 p.m. Fridays.

Paving must be performed during the daytime hours because of the warmer temperatures, Caltrans officials said.

One-way reversing traffic control will be enforced. Motorists can expect a delay not to exceed 15 minutes, Caltrans said.

Electronic message boards will be in place to notify the public of this work.

This project is expected to be complete by mid-October. The contractor for the $975,000 project is Granite Construction of Santa Barbara.